SOOOO MUCH has been happening that I haven't had the time to update! for the past few weeks we have been painting. EVERYTHING! It took a lot longer than I thought! after several long days and the help of family members, we got it done! I am really bad and did not take any pictures! sorry! there are still some areas that we need to touch up, but for the most part, the painting is DONE! Now we have to go through the house and use caulk on the base boards and around all the counter tops. the counter tops are supposed to be delivered today.
When we stopped by the house last night we were happy to see that all of the light fixtures have been installed, and we have a garage door! We also got a thermostat, and the air conditioning unit! Everything is coming together VERY quickly!
Kyle talked to our field manager last night and he told us that we could be closing Nov. 17th! That is less than 2 weeks away!!
AAAHHHH!
On the to do list:
flooring
final HVAC
final plumbing
counter tops installed
caulking
touch up paint
buy and install garage door opener
buy and install garbage disposal
well inspection
final grade
driveway improvements
I'm sure there are other inspections and things that the field manager has on his list that we don't know about but thats all I can think of!
We are starting to see the light!!
No comments:
Post a Comment